The calendar on the Task page does not align itself to the page
2018-02-27 13:51:33
Aditi Shankar
  • Visit: 15
  • Join Date: 2018-02-24
  • Last Login: 2018-03-21
  • My Point: 0
  • PartyLevel: No Party

The calendar on the Task page appears below the Plan window. It does not align itself with the position of the page.

Last edited by Aditi Shankar on 2018-02-27 17:27:15
2018-03-01 13:07:53
Aditi Shankar
  • Visit: 15
  • Join Date: 2018-02-24
  • Last Login: 2018-03-21
  • My Point: 0
  • PartyLevel: No Party

Steps to reproduce the error,

Go to Project>Create Task

Click the Plan and Deadline fields.

The calendar does not orient itself to the page but always appears below the Plan and Deadline fields. The user cannot see the calendar clearly.



2018-03-01 13:40:10
Pedro
  • Visit: 358
  • Join Date: 2017-11-07
  • Last Login: 2018-09-30
  • My Point: 0
  • PartyLevel: No Party
Although we could scroll to display the calendar, we would mark this as a issue to solve.Thanks.